Downtown I-670 to Close for Park Construction

Plan alternate routes now, since Interstate 70 closes for about 11 months starting January 11, 2027.

Updated on Nov. 18, 2026 in National Parks

Wide view of a downtown freeway trench under a concrete deck with steel formwork, a crane silhouette, and orange barrels, flanked by brick buildings.
Interstate 670 downtown will close December 2, 2026, for about two years as crews build Roy Blunt Luminary Park over the highway, with the work expected to finish in spring 2029. AI Illustration. Upload story photo >

Live Poll

Do you support long-term downtown construction even with years of traffic disruption?

Kansas City drivers and downtown neighbors face a long stretch of closures starting December 2, 2026, when Interstate 670 and downtown streets shut for construction of Roy Blunt Luminary Park. The park will sit above the highway, and the work is expected to run until spring 2029.

Why it matters

The park is meant to reconnect neighborhoods that the highway split apart in the 1960s, but the construction will reshape how people get downtown for years before any green space opens. Residents who drive, bike or ride transit through the core should plan for the disruption now.

The city's schedule puts Interstate 670 out of service from December 2, 2026 through about September 2028, with downtown street closures running until spring 2029 and a roughly 11-month Interstate 70 closure beginning January 11, 2027. Severe winter weather could push the I-70 start back, and the source does not confirm the park's final opening date.

The players

City of Kansas City, Missouri

The city government is leading the Roy Blunt Luminary Park project and is hosting the public information session.

The details

Construction of Roy Blunt Luminary Park begins in December 2026 on a deck above Interstate 670 in downtown Kansas City, extending from Bartle Hall to the former Kansas City Star press site. Planned amenities include green space, walking trails, inclusive play areas, art and entertainment space, and room for food trucks and community events. Drivers should expect the I-670 closure to start December 2, 2026, and the city recommends Interstate 435, Interstate 35 and U.S. 71 as alternate routes while the work proceeds.

Timeline

  1. November 23, 2026: Kansas City hosts a virtual information session at 6 p.m. on the project.

  2. December 2, 2026: Interstate 670 and downtown street closures begin as construction starts.

  3. January 11, 2027: An approximately 11-month Interstate 70 closure between Prospect Avenue and Van Brunt Boulevard is scheduled to begin.

  4. September 2028: Interstate 670 is expected to reopen.

  5. Spring 2029: Downtown construction is expected to be completed.

The Heart of America View

The downtown highway that went up in the 1960s split neighborhoods apart, and this project tries to stitch them back together by building a park on top of the same corridor. It is a deliberate reversal of that earlier decision, though it will first take years of closures to deliver.

If you commute through downtown, expect the I-670 closure to reroute your drive for nearly three years, so check alternate routes on I-435, I-35 and U.S. 71 before December. Plan extra time for the January 2027 Interstate 70 closure, which runs about 11 months.

The takeaway

Kansas City drivers should map alternate routes now, before the December 2 closure begins. Watch for the November 23 information session and the January 11, 2027 Interstate 70 start date.

What happens next

The virtual information session takes place November 23, 2026 at 6 p.m., and Interstate 670 closes December 2, 2026. The Interstate 70 closure is set to begin January 11, 2027, subject to winter weather delays.

Further reading

Explore more about National Parks to see how urban green spaces fit alongside larger public landscapes.

Source note: This article includes information reported by Kctv5.